| 3rd September 2004. Roof is finished just in time for the autumn rain. Rendering and rough casting on the rear walls is taking place between the rain showers. Work inside is progressing well with some walls being plastered as the "first fix" is under way | |
| 21st September 2004 Internal plastering is finished, Electrical "first fix" is finished, some under floor insulation has been laid and finishing touches to the outside continue between rain showers. | |